The foundation under your shed decides how well the building performs for its whole life. A good one keeps the floor level, the frame dry and the structure anchored. A poor one means cracking, pooling water and frame corrosion, plus a slab that is hard to fix once the concrete has cured.
This guide walks through the decisions that matter most: which foundation your shed needs, how thick a slab should be for different uses, and what the permit rules look like in Victoria. It is written for property owners planning a shed build, not for engineers, so you can talk to a builder with confidence.
Key Takeaways
- Not every shed needs a concrete slab. Pier footings and screw piers suit open-sided shelters and difficult sites, but they do not replace a floor where one is needed.
- Slab thickness varies significantly by use. A domestic garden shed typically needs 100mm of reinforced concrete, while a farm machinery shed typically needs 125mm to 150mm with heavier steel mesh.
- Anchor bolts must be cast into the slab before it cures. Drilling anchors into a cured slab later is possible but weakens the slab and adds cost.
- In Victoria, only a small freestanding Class 10a shed can be exempt from a building permit. Planning and bushfire overlays can add requirements, so your local council is the place to confirm what applies.
What Type of Foundation Does a Shed Need?
The answer depends on four things: shed size, intended use, load on the floor and soil conditions on your site. There is no single correct foundation for every shed.
The three main options are a poured concrete slab, pier footings and screw piers, and each suits different conditions:
- Concrete slab: the right choice where the floor will be driven on, loaded with machinery or equipment, or used for storage that needs a level, hard surface.
- Pier footings: suit open-sided shelters and structures on uneven ground.
- Screw piers: suit sites where concrete access is restricted or conventional footings are impractical.
Site preparation matters before any option is finalised, because soil type, drainage patterns and slope all affect the specification. Trusteel Fabrications assesses site conditions as part of its design and quoting process. Once you have worked through the options below, the site preparation checklist covers the practical steps for getting your site ready.
Concrete Slab: When It Is the Right Choice
A concrete slab is the most common foundation for steel sheds in Victoria, and for good reason. It provides load-bearing continuity across the full shed floor, which matters when vehicles drive over it or equipment sits on it for long periods.
A slab also suits a frame with Rectangular Hollow Section (RHS) structural steel base rails. The rails sit flush against the slab surface, and the anchor bolts connecting frame to slab must be cast in at precise positions before the concrete is poured. Formwork has to be set with bolt positions matching the shed’s base rail layout. If a separate contractor pours the slab from incomplete specifications, the bolt positions may not line up with the frame when it arrives.
Core-drilling a cured slab to add anchors later is possible, but it is not ideal. It weakens the slab around the drill point and adds cost. Cast-in anchors are the standard approach, which is one reason having the same builder manage slab and frame reduces risk.
Slab Thickness by Use Case
Slab thickness is not a single figure. A structural engineer or building surveyor sets the specification from your soil classification, the loads the floor will carry and the size of the structure. The figures below are typical ranges used across Victoria, and an engineer confirms what applies to your site.
Domestic garden shed or garage
- Standard minimum: a 100mm reinforced concrete slab with SL72 steel mesh reinforcement suits most domestic applications.
- Unreinforced option: a 75mm slab may serve a very small, lightly loaded garden shed, but it is not appropriate where a vehicle, ride-on mower or loaded pallet will cross the floor.
- Soil classification: AS 2870 (residential slabs and footings) affects what the engineer specifies. Reactive clay soils, common across Melbourne, may need edge thickening or deeper perimeter footings to manage soil movement.
- Base and moisture: a compacted gravel base is standard on most sites, and a vapour barrier between the gravel and concrete reduces moisture migration through the shed floor.
Farm machinery or rural shed
Tractors, headers and hay bales impose much heavier loads than a domestic garage. Farm machinery sheds typically need a slab of 125mm to 150mm with SL82 mesh or an engineer-specified reinforcement schedule, and edge beams are standard. Point loads from jack stands and outrigger feet belong in the slab design from the start. The larger footprint also means formwork setup and concrete volume rise significantly compared with a residential pour.
Commercial or industrial shed
At the commercial and industrial end, a concrete slab is an engineered structure in its own right. Compressive strength is typically specified at N32 or above, and post-tensioned slab designs may be used where forklift loads, heavy racking or car hoist anchors exceed what a standard reinforced slab can carry. An engineer’s report is standard.
NCC building classification affects the requirements as well. A Class 7b warehouse shed has different obligations from a Class 10a domestic shed, and a use involving manufacturing or processing changes the classification again.
Pier Footings: When They Make Sense
Pier footings suit open-sided shelters, paddock shelters, shade structures and carports where no enclosed floor area is needed. They are also worth considering where terrain is uneven enough that excavating a level pad would take significant earthworks.
Piers can be poured in place or precast. They use less concrete and cost less than a full slab, but they do not provide a usable floor. A shed that needs a floor for storage, vehicles or equipment still needs a slab over or alongside the piers.
Pier footings are not a cost-cutting shortcut for sheds that need a floor. They are a genuinely different solution for a genuinely different use, and understanding that early saves significant rework later.
Screw Piers: A Faster Option for Certain Sites
Screw piers are a growing alternative where concrete truck access is restricted, soil is unstable or the structure may need to be relocated. They are driven into the ground mechanically without excavation, and they can reach bearing depth faster than poured footings on reactive or sandy soils.
Their limitations are real:
- A structural engineer must specify the diameter and depth for each site.
- They do not suit every shed type or soil condition.
- They are a foundation system, not a floor system, so a slab is still needed for a usable internal floor.
Trusteel can advise on whether screw piers are appropriate for a project once site conditions are known.
Drainage: The Detail Most People Miss
A slab poured dead flat will pool water against the shed’s base rail during heavy rain. Standing water accelerates corrosion of steel components, and it can also affect the manufacturer’s warranty coverage.
The formwork must be set with a slight slope away from the building on all sides. That is a planning step, not something corrected after the pour, so the drainage gradient has to be built into the formwork before any concrete is placed.
A perimeter edge rebate is also worth specifying. The slab edge is formed slightly lower than the internal floor level, so the base rail sits proud of any surface water running along the edge. Like anchor bolt placement, this detail needs one shared design. When two contractors manage slab and frame, the coordination step is easy to miss. When one builder manages both, it is a standard part of the process.
Do You Need a Building Permit for a Shed Slab in Victoria?
In Victoria, the Building Regulations 2018 set when a building permit is required. Most sheds that need a proper slab are larger than the exempt size, so a building permit usually applies.
When a shed can be exempt
A freestanding Class 10a shed (a non-habitable ancillary building) can be exempt only if it meets all of these conditions, according to the VBA’s building practice note:
- A floor area of 10 square metres or less
- A height of no more than 3 metres, or 2.4 metres within 1 metre of a boundary
- Not built of masonry
- Compliance with siting conditions
The same note says excavation for an exempt shed is also exempt.
Planning and bushfire requirements
A planning permit may also apply, depending on your zone and overlays. Council requirements vary by zone, so a rural property and a residential property can face quite different rules for the same shed size.
Bushfire-prone land adds another layer. A property’s Bushfire Attack Level (BAL) rating shapes construction detailing, and a bushfire overlay can bring planning requirements even for a small shed. VicPlan shows the overlays on your property.
Confirming what applies
Your local council or a registered building surveyor can confirm what applies before you pour. As a registered VBA builder, Trusteel Fabrications manages permit applications where required. It engages the registered building surveyor on your behalf, so you do not need to navigate that process independently.
Slab Cost as Part of the Total Shed Build
The concrete slab is often what surprises buyers who have only priced the steel kit. It represents a meaningful share of the total project cost, and it varies with slab thickness, floor area, soil preparation and the concrete mix strength the engineer specifies.
An accurate slab quote depends on knowing the shed’s base dimensions. That is why Trusteel’s quoting process captures slab requirements early, alongside the frame specification. Melbourne concrete pricing fluctuates, and a quote based on approximate dimensions will not stay accurate once the actual base rail layout is confirmed.
The better approach is to quote slab and frame together from a single builder, so there are no gaps between contractors, no conflicting specifications and no dispute over who is responsible if the two components do not align. For the full picture of what a build costs, see shed prices and quoting, and for the wider construction sequence, our guide on how to build a large shed.
How Trusteel Manages Slab and Frame as One Coordinated Build
Three problems come up again and again on shed foundations. Anchor bolt positions have to match the frame. Drainage gradients have to be set in the formwork before the pour. Permit requirements change from one zone to the next.
All three come down to the same thing: the slab and the frame need to be planned together, as one project. When they are, details like bolt alignment and drainage fall are settled on paper first, not discovered on site after the concrete has cured.
Trusteel Fabrications builds around that principle. Slab, frame and permits are managed as one coordinated build, which is what the sections below explain.
One point of accountability
When two separate contractors manage the slab and the frame, accountability gaps appear. If the slab is wrong, the shed builder points at the concretor, and if the frame does not fit, the concreter points at the shed specifications. When Trusteel Fabrications manages the full project, there is one point of accountability from design through to installation. Anchor bolt positions are confirmed against the frame layout before formwork is set, and drainage fall is built into the slab specification. These are not extras. They are part of how a coordinated build works.
A registered VBA builder
Trusteel’s VBA registration means the full construction process is managed under one registered builder, with no separate registered builder needed. Permit applications, where required, are handled by Trusteel. The customer’s job is to brief the project and confirm the design, not to coordinate between trades. That matters most where site conditions, slab specification and frame design all have to work together from the start.
To plan a shed build in Victoria, get advice on your shed foundation and permit pathway from Trusteel and we will talk through foundation type, slab specification and the permit process for your site.
Frequently Asked Questions
How thick should a concrete slab be for a garden shed?
Most domestic garden sheds in Victoria sit on a reinforced slab of around 100mm. Very small, lightly loaded sheds sometimes use an unreinforced 75mm slab, but that suits only a floor kept free of vehicles and loaded pallets. An engineer or building surveyor confirms the final specification against your soil classification.
Do I need a building permit to pour a shed slab in Victoria?
Most shed slabs in Victoria need a building permit, because the exemption only covers freestanding Class 10a sheds of 10 square metres or less within height and siting limits. A planning permit may also apply depending on your zone and any bushfire or other overlays. Your local council can confirm what applies before you pour.
How much does a concrete slab cost for a shed, and is it included in the shed price?
A steel shed kit price typically does not include the concrete slab. Slab cost varies with thickness, floor area, soil preparation and the concrete mix strength specified. A domestic garage slab and a commercial machinery shed slab can differ substantially in cost per square metre. Trusteel quotes slab and frame together, so buyers receive a complete project figure.
Can I pour a shed slab myself, or does it need to be done by a professional?
A small garden shed slab may be within a capable owner-builder’s ability, but mistakes in bolt positions or drainage fall are expensive to fix once the concrete cures. For anything larger than a basic garden shed, a professional concretor working from the shed builder’s specifications is the lower-risk approach.
What is the difference between a concrete slab, pier footings and screw piers for a shed?
A concrete slab provides a continuous floor and is the standard base for enclosed sheds used for storage, vehicles or machinery. Pier footings are point foundations suited to open-sided shelters and uneven terrain, and screw piers are a faster alternative on difficult or restricted-access sites. Neither provides a floor, so a shed that needs a usable internal floor still needs a slab.